This dialog is available at the process level. To display it, do one of the following:
● click on an empty area in the flowsheet and then click Process Options } Operating Cost Options on the Edit menu, or
● right-click on the flowsheet to display its context menu and then click Operating Cost Options.
If the Labor Requirements Are Per Oper-h and Per Equip option is checked then the labor demand of the operation can be interpreted as labor hours per operating hour and per equipment. Therefore when calculating the labor amount of an operation which is using multiple equipment units simultaneously (in parallel), then we must multiply the amount by the number of units.
The following table shows a brief description of the variables appearing in this tab; for more details, see Operating Cost. The table also displays their default values and their generally acceptable range:
Variable |
Default Value |
Range |
|
||
○ Raw Materials |
No |
Yes/No |
○ Labor-Dependent Entries |
No |
Yes/No |
○ Facility Cost Dependent Entries |
No |
Yes/No |
○ Consumables |
No |
Yes/No |
○ Laboratory, QC, QA Cost |
No |
Yes/No |
○ Waste Treatment and/or Disposal |
No |
Yes/No |
○ Utilities |
No |
Yes/No |
○ Transportation |
No |
Yes/No |
○ Miscellaneous |
No |
Yes/No |
Symbol Key: ○ User-specified value (always input); ● Calculated value (always output); ◙ Sometimes input, sometimes output