Operations Gantt Chart Style Dialog: Contents Tab

OpGCStyle_ContPP.jpg

This property page is part of the Operations Gantt Chart Style Dialog.. This is the dialog for editing the graph style of the Operations Gantt Chart (single or multiple batches).

Specification Choices / Comments

The following list describes the available specification choices in this tab.

Grid: Include Columns...

Check the columns that you wish to see displayed on the grid view side of the interface.

Chart / Grid: Include Summaries...

The following is the full list of abstraction (summary) layers that can be present:

1.   Operation

2.   Cycle

3.   Procedure

4.   Section

5.   Branch

6.   Batch

If you wish to omit any of the mentioned intermediate summary levels, then please uncheck the corresponding check boxes.

Include Equipment Name (in Procedure Name)...

If this option is checked then the name of the procedure appearing on the chart will also include the name of the equipment that hosts the procedure.

Order / Include / Exclude Procedures...

If you click on this button, you will be presented with the process-maintained procedure list. This is the list that is employed when displaying the procedure on the chart. If you modify the procedure order this will not only affect the procedure displayed on this chart but also in any other charts and/or tables where the custom order is followed (e.g. the procedure utilization breakdown table). The procedure order list can also be edited by selecting Include / Exclude / Order Procedures from the chart’s command menu or by selecting Preferences } Procedure Order from the flowsheet’s command menu.

Grid Text Color / Font

With these controls you may set the desired text font style and color that appears in the grid.