The following table shows the meaning of the variables appearing in this tab, as well as their default values and their generally acceptable range. Note that due to the manner by which the variables are used by the sizing and costing equations, the range of acceptable values may be further reduced.
Variable |
Default Value |
Range |
|
||
◙ Evaporative Capacity Rate |
0.0 kg/h |
Positive |
◙ Max Evaporative Capacity |
18,000 kg/h |
Positive |
Symbol Key: ○ User-specified value (always input); ● Calculated value (always output); ◙ Sometimes input, sometimes output
In Calculate (Design Mode), the user specifies the Maximum Evaporative Capacity and the system computes the Number of Units and the Evaporative Capacity.
.
In User-Defined (Rating Mode), the user specifies the Number of Units, the Evaporative Capacity.
For costing purpose it is assumed, H2O removed represents 80% of the total feed throughput. It was derived assuming a feed solids content of 5% and a dried sludge solids content of 35%. The equipment cost is a function of the evaporative capacity rate.
For more information on this equipment, see Sludge Dryer.
For information on the left-hand side variables and options, see Equipment Data Dialog: Equipment tab.