Load and Split: Split Tab

LoadAndSplitSeparation.jpg
Variable Definitions, Ranges and Default Values

The following table shows a brief description of the variables appearing in this tab. The table also displays their default values and their generally acceptable range:

Variable

Default Value

Range

 

Port / Stream #1
Indicates the output port that is connected to split stream #1. Click on the list box to bring up a list of available output streams in order to select one.

<None>

Any Output Port

Port / Stream #2
Indicates the output port that is connected to split stream #2. Click on the list box to bring up a list of available output streams in order to select one.

<None>

Any Output Port

% to Stream #1
The percentage of a component that is split to stream #1.

0.0

0-100

% to Stream #2
The percentage of a component that is split to stream #2.

0.0

0-100

Symbol Key: User-specified value (always input); Calculated value (always output); Sometimes input, sometimes output

Specification Choices / Comments

The following list describes the available specification choices in this tab; for more details on how these are implemented, see Load and Split: Modeling Calculations.

If you want to remove some material as the simultaneously to the loading operation you can do this by specifying up to two output streams (port 1 / port 2).

For each component present in the process you can specify the percentage of its amount in the equipment that is to be removed via ports 1 & 2. The sum of the components percentage in these two streams cannot exceed 100.